Air and wall temperature
Every pack of skim, primer and paint states a minimum application temperature — usually +5 to +10°C. It applies not only to the air but also to the surface. An external wall in a cool room can be noticeably colder than the air by the radiator.
Switch the heating on a day or two before work and do not turn it off at night until everything has dried. A drop in temperature at night slows drying and encourages moisture to condense on the walls.
Moisture: air the room briefly and thoroughly
Skim and paint dry by releasing water into the air. In winter the cold outside air holds little water vapour, so opening the windows wide for a short time several times a day exchanges the damp air well. A window left permanently ajar only chills the walls and lengthens drying.
Do not heat rooms with a gas heater. Burning gas produces water vapour, so instead of drying it adds moisture. Electric heating or a building dehumidifier works better — especially in a new house where fresh plaster and screeds are still giving off water.
Skim coats: thin layers and patience
Apply skim in thin layers and put on the next one only when the previous one is completely dry. In winter, treat the drying time on the pack as a minimum, not the norm.
Do not point a heater or fan straight at fresh skim. A surface that dries too fast while the inside of the layer is still wet cracks in a web of fine lines that only show after painting.
Sanding and checking against the light
Only sand skim that is completely dry. Damp filler clogs the paper and tears out in pieces. On large areas, a long-reach sander connected to an industrial vacuum that collects most of the dust saves your arms and neck.
Unevenness shows best in light falling along the wall. Put a work light to the side, almost parallel to the surface, and inspect the wall before priming — after painting, corrections are much harder.
Plasterboard in winter
Before fitting, plasterboard should lie in the room where it will be used so that it takes on its temperature and humidity. A board brought straight from a freezing garage and screwed up at once can change size slightly after a few days, and cracks appear at the joints.
Fill the joints with reinforcing tape and only in a heated room. Jointing compound dries longer in winter, so apply the next coat when the previous one is fully dry, even if the pack gives a shorter time.
Primer before you paint
After sanding, vacuum the wall and prime it. Primer evens out absorption: where the skim was thicker, unprimed paint soaks in differently from the area next to it and leaves dull patches. In winter primer dries longer — wait for the time on the label before painting.
Painting
Keep the paint in a warm room, not in the garage. Cold paint thickens and spreads worse. Paint in good light, wet on wet, the whole wall from corner to corner without stopping — a break halfway across the wall leaves a visible line.
Apply the second coat after the time on the label, extended at lower temperatures. With dark colours on a light surface, expect a third coat. You can work out how many litres to buy with the calculator on the paints page.
How much time to plan
In winter finishing work takes longer than in summer because every stage has to dry. For a room with new skim, allow several days: two coats of skim, sanding, primer and two coats of paint, each with a break for drying. Trying to speed things up by shortening the breaks usually ends in redoing work.
If the house is new and the plaster and screeds were done in autumn, add time for them to dry before skimming. Moisture from the walls comes out through fresh paint and leaves stains on it.